a) Burnie Cultural Precinct – BAFC Redevelopment (Stage 2) – Contract 2711
Demolition of the internal courtyard has been completed. Excavations for footings, including the lift shaft are poured and blocks for the lift shaft have arrived on site. Steelwork erection for the new Atrium space will commence in July. The lower ground back of house areas are complete and these have been handed back to BAFC for storage use. Zinc cladding to the north external wall is complete except for areas adjacent new northern canopy.
b) Bitumen Surfacing Services 2023-2024 – Contract 2705
Hardings have completed the reseal program with the following roads completed Alma Place, Kennedy Street, Bernard Place, Boland Avenue, Brickport Road, George Street, Grandview Avenue, Ocean View Lane, Pearl Street, Ogden Street and Latrobe Street.
c) Mount Street/Three Mile Line Road Roundabout Construction – Contract 2703
Walters Contracting have commenced onsite and are steadily progressing. Works for kerb preparation have been completed with kerbs to be poured in July. Whilst some initial issues with Traffic Management the contractor quickly remedied. Works are due to be completed in August weather permitting.
d) Coastal Pathway – Contract 2702
Asphalt works is continuing and revetment of the banks to protect against erosion is underway. Landscaping works design has been completed and works will commence in August.
e) Burnie Gateway Project
The Artists have raised concerns around potential impact of rabbits, on site rabbit fencing has been installed to allow plants to established. Site works are now complete and Council are investigating options for the pedestrian crossing.
f) City Centre Urban Plan
The Draft Urban Plan is complete, and Council Officers are now commencing the Co-design component of the project. Feedback will be used to amend the design and the revised draft to be finalised and submitted to Council in December2024. Council Officers will look at the development of the working group to review and interpret the feedback into the final plan.
g) South Burnie Beach Boat Ramps Redevelopment – Timber Jetty Upgrade and Concrete Pier Works – Contract 2701
Hunter Diving and Marine Construction have completed works to the timber Jetty Refurbishment and jetty is now open to the public. Buildrite have commenced construction of the Stepped Concrete Pier. Landing Ramp 1 – 6 have been constructed and a portion of the FRP treading has been installed. Works are scheduled to be completed mid to late July.
h) South Burnie Beach Boat Ramps Redevelopment – Contract 2700
Hardings have recommenced works on site, they have completed additional work to the bund wall and road surface. Works are slightly delayed due to working around Buildrite and Hunter Diving and Marine Construction. Remaining works are scheduled to be completed by end of July.
i) Burnie Cultural Precinct – BAFC Redevelopment (Stage 1) – Contract 2694
Café cooking equipment delivery has been delayed but will be installed early July. Floor finish and glazing to Long Room space is complete. Soffit and external express cladding to entry canopy complete. Café external walls underway. Entry slabs complete with paving to commence in conjunction with external work.
j) Bitumen Surfacing Services 2022-2023 – Contract 2691
Contractor has completed the Thorne Street Remediation works to the satisfaction of Council’s Engineers.
k) Flood Recovery Projects
Oonah Road West
Works are now complete and road is operational.
Oonah Road East
Road remains closed from CH1030 to CH2770. The affected area dig out was slightly deeper than expected, over 27,000T of rockfill has been placed. BridgePro have completed removal sheet piling. Final road pavement works are substantially complete. The main section of road is scheduled to be completed mid-July.
Works to the culvert on the hairpin will commence after this section is completed. Due to the nature of reconstruction works, another section of pavement will need remediation works prior to the road being reopened to the public. This is due to the multiple HV loads of imported fill to the affected area, has had a detrimental impact on the road surface.
Upper Natone Road – Horseshoe Bend
Road remains under traffic management with a 5T load limit still in place. Drainage and landscaping works have been completed. Geotechnical report has supported the realignment of road section along Patons Creek. Consultant Engineers are progressing with design. Construction is scheduled to commence in late Spring.
Fernglade Road
Retaining wall construction has been completed with safety barrier reinstated. Sealing works will be completed as soon as practical. Road is still under traffic management until sealing is complete.