Futuna Ave and West Park Grove Roundabout Works

  • Contractor nameHardings Group
  • Completion Date23 April 2025
Futuna Ave Roundabout .png

Works to construct the roundabout at Futuna Ave and West Park Grove will commence on 13 January 2025. Harding's Group will be the contractor undertaking the works.

Works are expected to be completed by mid April 2025 (extended from the original completion date of mid March).

During the construction traffic control will be in place to lower speeds, and some delays may occur.

This project has received funding under the Australian Government Black Spot Program

Plan for Facebook.JPG

 

Updates: 

Monday 14 April 2025

From Monday 14th April to Thursday 17th April, Futuna Avenue will be closed from Paraka Street to West Park Grove.

Roundabout Construction Schedule:
  • Monday, 14th April: Begin deep lift placement at West Park Grove/ Futuna intersection.
  • Tuesday, 15th April: Start construction of the roundabout.
  • Wednesday, 16th April: Concrete pour for the roundabout with 60mpa
  • Thursday, 17th April: Asphalt installation around the roundabout to ensure safe navigation for vehicles.

Road closure and detour maps(PDF, 887KB)

 

Location

Futuna Ave and West Park Grove, Park Grove   View Map and directions

Google Map