Netball Centre - Court Resurfacing
- Project value$648,043.20
- Contractor nameHardings Group
- Completion Date31 March 2025
With thanks to the Tasmanian government for providing $400,000 in grant funding for this project
The asphalt on courts 3-8 at the Netball Centre is being replaced due to large cracks in the playing surface and surrounding areas, which pose a safety risk for both players and spectators. Additionally, the courts do not meet Netball Australia's requirement for a consistent 1% cross-fall grade, which needs to be corrected.
The works will include:
- Removal of the existing asphalt on courts 3 to 8.
- Base regrading to remove high/low points and soft areas.
- Drain replacement along the centre of the courts.
- Replacement of grates on outer drains.
- Installation of a new spoon drain.
- New asphalt with acrylic seal.
January updates
Removal of the existing asphalt has begun on courts 3 to 8.
Location
Burnie Netball Centre, Howe Street, Burnie 7320 View Map and directions